We ask the engineers working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineers tell us that activity A takes 2 weeks 25% of the time, 4 weeks 50% of the time and 6 weeks 25% of the time. How long does the project now take to complete (on average)

User Abourget
by
8.3k points

1 Answer

3 votes

Answer:

On average, the project takes 4 weeks to complete.

Explanation:

We have these following probabilities:

25% probability that the activity takes 2 weeks.

50% probability that the activity takes 4 weeks.

25% probability that the activity takes 6 weeks.

How long does the project now take to complete (on average)

We multiply each duration by it's probability.

0.25*2 + 0.5*4 + 0.25*6 = 4

On average, the project takes 4 weeks to complete.

User Ahmed Lotfy
by
7.8k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories