Answer:
$8,775 is the cost for both months
Step-by-step explanation:
In this question, we are asked to calculate total combined direct labor cost that forty winks corporation should budget in the months of March and April.
Let’s proceed!
To solve this question , we first calculate the total direct labor hours required.
Mathematically that can be calculated by ;
Production budget * Direct labor hour required per unit
For the month of March we have;
1,600 * 0.25 = 400
For April we have ;
1,100 * 0.25 = 275
We identify that the direct labor per hour rate = $13
For the month of March,
The total direct labor cost = 13 * 400 = $5,200
For the month of April;
The total direct labor cost = 275 * 13 =$3,575
The cost for both months is thus; $3,575 + $5,200 = $8775