Dynisco makes car transmissions of various sizes on a single production line. They forecast daily demand for transmission A at 90 per day. The plant runs 260 days per year. Their production line can produce 450 transmissions per day. The setup cost per production run is $225. The holding cost is $2/unit per years. What is the optimum production order quantity they should make each time they run transmission A

1 Answer

2 votes

Answer:

2565

Step-by-step explanation:

See attached file