Pete, a civil engineer, is appointed to build a state-of-the-art office building. He begins planning the design and construction of the building with his team. He estimates that the building would take six months to build and assigns work and material accordingly to the workers. In this scenario, Pete is specifying the ________.

User Pcbabu
by
3.8k points

1 Answer

1 vote

OPTIONS:

a. scatter plot

b. data model

c. baseline

d. line of code

Answer:

c. baseline

Step-by-step explanation:

Baseline is a term used in project management, which refers to the fixed line of reference that is stated clearly at the start of a project, and serves as a basis of comparison to measure the progress or how far and good a project has been successfully executed at any stage of the project.

The baseline of a project usually encompasses three aspects, which are; the schedule of the project, the cost, and the scope of the project.

According to the scenario described in the question above, we can imply that Pete is specifying the baseline of the project.