Answer:
149 loads of import will be required for the project.
Step-by-step explanation:
bank cubic yards = bcy
Loose cubic yards = lcy
Calculate for the required bank cubic yards.
Required bank cubic yards = required in place cubic yards/shrinkage
Substitute
required in place cubic yards = 1,490 ccy
shrinkage percentage = 95% = 0.95
Required bank cubic yards = 1,490/0.95 = 1,568.42 bcy
Determine the volume of the material to be transported
Loose cubic yards = bank cubic yards * (1 + swell percentage)
swell percentage = 14% = 0.14
Loose cubic yards = 1,568.42*(1+0.14) = 1,788 lcy
loads of import that will be required = Loose cubic yards/truck haul capacity
loads of import that will be required = 1,788/12 = 149 load