Answer:
15,160
Step-by-step explanation:
Net 20 terms: Full amount ready between 20 days, occasionally written as n/20.
Terms 2/10. n/30: with a 2% discount for settlement within 10 days, net 30 implying that the full amount will be ready between 30 days.
The terms 1/10, n/30: with a 1% discount for settlement within 10 days time, net 30 meaning the full amount is going to be ready between 30 days.
Terms 5/10, 2/30, n/60: 5% for settlement within 10 days, 2% for settlement in 11-30 days, full amount due within 60 days.
Net 30 Terms EOM: Payment will be ready in full 30 days after the end of the month (EOM) in which the invoice was given for.