Step-by-step explanation:
The computations are shown below:
1 As we know that.
Inspection time = Average throughput time - process time - average move time - average queue time
0.3 days = Average throughput time - 2.7 days - 1.0 days - 5.0 days
So, the average throughput time is 9 days
2. As we know that
Process time = Manufacturing cycle efficiency (MCE) × average throughput time
2.7 days = Manufacturing cycle efficiency (MCE) × 9 days
So, Manufacturing cycle efficiency (MCE) is 0.3 or 30%
3. Since the Manufacturing cycle efficiency (MCE) comes 30% of the through put time so the percentage is 70% percentage
4. As we know that
Wait time = Delivery cycle time - average throughput time
14.0 days = Delivery cycle time - 9 days
So, the delivery cycle time is 23 days
5. As we know that
Inspection time = Average throughput time - process time - average move time
0.3 days = Average throughput time - 2.7 days - 1.0 days
So, average throughput time is 4 days
Now the Manufacturing cycle efficiency (MCE) is
Process time = Manufacturing cycle efficiency (MCE) × average throughput time
2.7 days = Manufacturing cycle efficiency (MCE) × 4 days
So, Manufacturing cycle efficiency (MCE) is 0.675 or 67.5%