27. ___ is a method for developing the shortest schedule when the number or amount of available resources is fixed. a. Resource evaluation scheduling b. Resource monitoring c. Resource limited scheduling d. Resource leveling

User Jaymz
by
3.9k points

1 Answer

3 votes

Answer:

c. resource-limited scheduling

Step-by-step explanation:

Resource - limited scheduling -

As the name suggests ,

It refers to the method of scheduling the shortest schedule where the available resources are fixed , is referred to as the resource - limited scheduling .

It is a specific method to implement the resource leveling strategy in any assignment or project .

Hence , from the given information of the question ,

The correct answer is c. resource-limited scheduling .