In line balancing, takt time is the time___________.a. Needed to change over a process between different types of products b. It takes a product to go through the entire process c. That is the maximum allowable time at each workstation based on customer demandd. Required for the entire product fulfillment process

2 Answers

0 votes

Answer:C. That is the maximum allowable time at each workstation based on customer demand

Explanation: Line balancing is a term used in production to describe the time it takes in each work station based on customer demand, a Well-balanced line prevents labour idleness,laziness and ensures improved productivity and efficiency.

Take time is the average time it takes between the start of one product and the start of the next product based on the demands of the customer. Takt time is very essential for Productivity and efficiency a higher takt time means a lower Productivity.

User GilaMonster
by
5.0k points
7 votes

Answer: C. That is the maximum allowable time at each workstation based on customer demand

Step-by-step explanation:

Takt time is the rate at which parts or products must be produced in order to meet customer demand. For a given production line, if the production time is exactly equal to Takt time, then the line is perfectly balanced