2.6k views
0 votes
You are given the following information about a drybatch paving operation. You are going to use one mixer that has a service rate of 30 services per hour. The dry-batch trucks you use for bringing concrete to the paver have an arrival rate of 7.5 arrivals per hour. Each truck carries 6 cubic yard of concrete. You have a total amount of 13,500 cubic yard of concrete to pour. You rent a truck at $15 per hour and the paver at $60 per hour. If the job takes more than 80 hours, you pay a penalty of $140 perhour owing todelays injob completion. Onthe basis of least cost, determine the number of trucks you should use. Plot the cost versus the number of trucks used.

User Shangwu
by
4.5k points

1 Answer

6 votes

Answer:

Answer for the question:

You are given the following information about a drybatch paving operation. You are going to use one mixer that has a service rate of 30 services per hour. The dry-batch trucks you use for bringing concrete to the paver have an arrival rate of 7.5 arrivals per hour. Each truck carries 6 cubic yard of concrete. You have a total amount of 13,500 cubic yard of concrete to pour. You rent a truck at $15 per hour and the paver at $60 per hour. If the job takes more than 80 hours, you pay a penalty of $140 perhour owing todelays injob completion. Onthe basis of least cost, determine the number of trucks you should use. Plot the cost versus the number of trucks used.

is given in the attachment.

Step-by-step explanation:

You are given the following information about a drybatch paving operation. You are-example-1
You are given the following information about a drybatch paving operation. You are-example-2
User Qmeeus
by
3.8k points