Final answer:
The amount of work done in lifting the prestressed concrete beam is 21,614,928 ft • lb.
Step-by-step explanation:
To determine the amount of work done in lifting the prestressed concrete beam, we can use the formula:
Work = force x distance
First, we need to convert the weight of the beam from short tons to pounds:
1 short ton = 2000 pounds
So, the weight of the beam is 14 short tons x 2000 pounds/short ton = 28,000 pounds
Next, we can calculate the force exerted by the crane using Newton's second law:
Force = mass x acceleration
Using the given value of g (acceleration due to gravity) as 32.174 ft/s², we can convert the weight of the beam to force:
Force = 28,000 pounds x 32.174 ft/s² = 900,572 ft • lb/s²
Finally, we can calculate the work done by multiplying the force by the distance:
Work = 900,572 ft • lb/s² x 24 ft = 21,614,928 ft • lb
Therefore, the amount of work done in lifting the prestressed concrete beam is 21,614,928 ft • lb.