Answer:
The direct labor cost per unit is $0.55 as computed below.
Step-by-step explanation:
The direct labor-hour input that Kearney could allow and still achieve its profit goal of 30% of manufacturing costs for each of its product is calculated as:
Price =Direct material cost+Direct labor cost+overhead cost+profit %
let labor cost be y
Price=(9+30.7+y)*1.3
Price=39.7+y
since price =$70.20
Equation becomes:
70.20=(39.7+y)1.3
70.20/1.3=39.7+y
54=39.7+y
y=54-39.7
y=14.3
since direct labor hour is $14.3 per unit and direct labor cost per hour is $ 26 ,the labor-input required is 14.3/26 is $0.55