65.5k views
5 votes
The signing of the project charter represents all of these EXCEPT:__________

a. the formal approval of the detailed project schedule.
b. authorization to transition from high-level project initiation stage into the more detailed project planning stage.
c. a formal acknowledgement of the sponsor's commitment to the project.

1 Answer

5 votes

Answer:

A) the formal approval of the detailed project schedule.

Step-by-step explanation:

A project charter is an official document that acknowledges that a project exists, and it is given to the project manager by the project sponsor basically authorizing the transition from high-level project initiation stage into the more detailed project planning stage. It should include:

  • project title
  • goals and objectives
  • description and statement
  • key project deliverables
  • key milestones
  • stakeholders
  • constraints and risks
  • cost estimates
  • name of the sponsors, authority levels, manager

User Bill Kary
by
4.2k points