1. Every installation is to be properly protected near the point of entry of supply cables by a two-pole linked main switch and a fuse unit. In a two-wire installation if one pole is permanently earthed, no fuse, switch or circuit breaker is to be inserted this pole. A 3-pole switch and fuse unit is to be used in 3-phase supply.

2. The conductor used is to be of such a size that it may carry load current safely.

3. The conductors installed are to be safe in all respects.

4. Every sub-circuit is to be connected to a distribution fuse board.

5. Every line (phase or positive) is to be protected by a fuse of suitable rating as per requirements.