214k views
1 vote
PS.74 Bell computer is planning to launch a new high-end server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to be 90 units and there are three 8-hour shifts available each day to meet this production quota.

Task

Req'd Time (in minutes)

Predecessor

A

12

None

B

13

A

C

5

B

D

4

B

E

13

A

F

6

C,D

G

7

F

H

11

E

I

6

G,H

What is the total time, in minutes, to produce one server?

What is the takt time (in minutes) for this production line? (Your answer should be a whole number.)

What is the theoretical minimum number of workstations required for this production line? (Round up your answer to the nearest whole number.)

After assigning task A to workstation 1, which task (or tasks) should you assign to workstation 2? (In the field below, write the number that corresponds to your answer. Do not put a period after the number.)

B

C

D

E

B or E

C and D

Suppose you assign task B to workstation 2, which task (or tasks) should you then attach to workstation 3? (In the field below, write the number that corresponds to your answer. Do not put a period after the number.)

E and H

E

E or C, D, and F

C and D

Assume you assign tasks C, D and F to workstation 3, task E to workstation 4, which task (or tasks) should you assign to workstation 5?

G and H

G and I

H and I

H

What is the cycle time (in minutes) for this production line?

What is the overall efficiency for this production line? (percentage)

User Seoester
by
7.6k points

1 Answer

2 votes
So if you do this correctly you will get b
User Ramaral
by
8.1k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories