Which of the following terms is not used in project management? A. Dummy activity. B. Latest finish. C. Optimistic time. D. Lumpy demand.

User Tobi Nary
by
8.3k points

1 Answer

2 votes

Answer:

Lumpy demand is not used in project management.

The correct answer is D

Step-by-step explanation:

Dummy is a zero activity, which helps in network analysis.

Activity refers to a task in network analysis.

Latest finish time is the latest completion time of a project in network analysis.

Lumpy demand refers to low demand as a result of higher cost. It is not used in network analysis (project management)