Answer:
A. Constraint
Step-by-step explanation:
A project constraint is a limit to a project. The three most common types of project constraints are:
- Scope constraint - the project can be very ambitious and try to become a market leader, or it can be very niche and limited in scope.
- Budget constraint - the project can have a very large budget, or it could be limited by very scarce economic resources.
- Time constraint - the project might have to be completed in a long or in a short period of time.
In this case, as a project manager of BHY, your project has a time constraint: you must completed it by December 1, no matter what.