Answer:
The expected total cost of the units produced is d)$42,000
Step-by-step explanation:
Total fixed cost = Fixed cost per unit x units are plan produced = $3 x 5,000 = $15,000
Total fixed cost is not change.
Production is actually 4,500 units. Variable cost per unit is budgeted to be $6.00
Total Variable cost = Variable cost per unit x units are actually produced = $6 x 4,500 = $27,000
Total cost = Total Variable cost + Total fixed cost = $27,000 + $15,000 = $42,000