Except in rare circumstances, project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.

a. True
b. False

User Hayk
by
7.7k points

1 Answer

4 votes

Answer:

The statement is False

Step-by-step explanation:

Work packages is the one which is described as the group of the tasks which are related within the project. As the work packages look like the projects themselves, and they are usually the sub- projects from the larger or big project.

The statement is false as work packages does not provide the sufficient detail for developing the schedule of the project as the work packages are the smallest unit of the work and the group of the tasks related to the products.