84.8k views
4 votes
The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the ______:

User Ppreetikaa
by
7.7k points

1 Answer

3 votes

Answer:

The answer is Work Package.

Step-by-step explanation:

Work Package is the work component at the lowest level of the work breakdown structure(WBS), for which cost and duration can be estimated and managed; beyond this level, further decomposition will not be done.

Work packages are the primary input to identify activities' process. They are planned by way of identifying activities under them.

User Flex
by
8.0k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories