Answer:
The answer is Work Package.
Step-by-step explanation:
Work Package is the work component at the lowest level of the work breakdown structure(WBS), for which cost and duration can be estimated and managed; beyond this level, further decomposition will not be done.
Work packages are the primary input to identify activities' process. They are planned by way of identifying activities under them.