The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the ______:

User Ppreetikaa
by
5.1k points

1 Answer

3 votes

Answer:

The answer is Work Package.

Step-by-step explanation:

Work Package is the work component at the lowest level of the work breakdown structure(WBS), for which cost and duration can be estimated and managed; beyond this level, further decomposition will not be done.

Work packages are the primary input to identify activities' process. They are planned by way of identifying activities under them.