What is the earliest the project could be completed if tasks were ""crashed""?

User Axeltaglia
by
5.1k points

1 Answer

4 votes

Answer:

  • Crashing of task in Projects- "The process in which the total time or schedule of the project is reduced to a certain point by adding more resources to complete the tasks in it."

Step-by-step explanation:

And there are two main methods to obtain the required results, which are;

  1. Reduce the project requirements or scope: To reduce the project's requirements the restrictions are imposed on the securing of the budget to add more resources to complete the project.
  2. Adding additional resources to the critical path tasks:By increasing the number of resources and adding up more path ways we can complete the project in less time.