Answer:
- Crashing of task in Projects- "The process in which the total time or schedule of the project is reduced to a certain point by adding more resources to complete the tasks in it."
Step-by-step explanation:
And there are two main methods to obtain the required results, which are;
- Reduce the project requirements or scope: To reduce the project's requirements the restrictions are imposed on the securing of the budget to add more resources to complete the project.
- Adding additional resources to the critical path tasks:By increasing the number of resources and adding up more path ways we can complete the project in less time.