Answer:
6 days
Explanation:
1 boy workload = 1/2 1 man workload
2 boys workload = 1/2*2 = 1 man workload
so 3 men + 2 boys workload = 4 men workload
3 men ..... 8 days ... 24man-days to build
4 men ..... x days ... 24man-days to build
x=24/4=6