An engineering company needs to solve a design problem. it is a high speed train to transport passengers between Boston and Atlanta.

Which statement is a constraint for this project?

A. the train must have a dining car in which meals are served.

B. The train must be able to complete the trip in six hours,

C. The train must be able to carry at least 300 passengers.

D. The train must cost less than 6 billion to build.

1 Answer

5 votes

Answer:

D

Step-by-step explanation:

this makes limitations to the amount they can do