32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the same work by 16 workers working 8 hours per day?
asked
Jul 22, 2022
13.6k
views
5
votes
32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the
same work by 16 workers working 8 hours per day?
Mathematics
high-school
Thomas Vervest
asked
by
Thomas Vervest
7.7k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
4
votes
Answer:
45 days
Explanation:
Total man hours:
32*30*6 = 5760
Required days:
5760/(16*8) = 45
Brandon Haugen
answered
Jul 28, 2022
by
Brandon Haugen
7.0k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
7.5m
questions
10.1m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
How do you estimate of 4 5/8 X 1/3
Write words to match the expression. 24- ( 6+3)
A dealer sells a certain type of chair and a table for $40. He also sells the same sort of table and a desk for $83 or a chair and a desk for $77. Find the price of a chair, table, and of a desk.
The cost of 5 similar digital cameras and 3 similar video cameras is 3213. Each video camera costs 4 times as much as each digital camera. John buys a digital camera and a video camera. How much does he
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org