13.6k views
5 votes
32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the

same work by 16 workers working 8 hours per day?

1 Answer

4 votes

Answer:

  • 45 days

Explanation:

Total man hours:

  • 32*30*6 = 5760

Required days:

  • 5760/(16*8) = 45
User Brandon Haugen
by
5.5k points