Three workers can do a job in 28 hr. how many more workers are needed to do this job in 12 hours?

1 Answer

8 votes

Answer:

7 workers

Explanation:

The fewer workers there are, the fewer hours are required, and the more workers there are the fewer hours are required. Therefore workers and hours are inversely proportional. So, 7 workers can do that job in 12 hours.