Answer:
$5.47M
Step-by-step explanation:
The required endowment from the sponsor is the total costs required immediately plus the present value of the new equipment that needs to be purchased every five years as shown thus:
Immediate costs=cost of lab construction+cost of equipping the lab
Immediate costs=$2.5M+$1.2M
Immediate costs=$3.7M
Present value of every 5 years equipment cost=cost/(1+interest)^n-1
interest rate=6%
n=5 years(the frequency of incurring the cost)
PV=$0.60M/(1+6%)^5-1
PV=$0.60M/0.33822558
PV=$1.77M
required endowment =$3.70M+$1.77M
required endowment =$5.47M