Answer: $300,000
Step-by-step explanation:
As overhead is applied on the basis of direct labor cost, the overhead rate for the period is:
= Overhead / Direct labor cost * 100%
= 5,340,000 / 890,000 * 100%
= 600%
If direct labor cost is $50,000 then overhead applied will be:
= Direct labor cost * Overhead rate
= 50,000 * 600%
= $300,000