Joshua has been working as a project manager in an information technology company for three years. Martha is a delivery team lead in the same company. When the company receives a project that has to be completed in a short span of time, Joshua decides to increase the daily work hours of the delivery team to accommodate the project. Martha, however, insists that Joshua request the client for a time extension. Not willing to reach an agreement, Joshua and Martha ignore each other's opinions and begin working on the project individually. Which of the following conflict-handling intentions does this scenario portray? Collaborating Accommodating Avoiding Compromising

1 Answer

3 votes

The conflict-handling deals with collaborating