Answer:
the manufacturing cycle efficiency (MCE) is 0.28
Step-by-step explanation:
The computation of the manufacturing cycle efficiency (MCE) is shown below:
Manufacturing cycle efficiency is
= Value-added time (Process time) ÷ Throughput time
= 3.7 ÷ (3.7 + 0.7 + 3.3 + 5.4)
= 0.28
Hence, the manufacturing cycle efficiency (MCE) is 0.28
We simply applied the above formula so that the correct value could come