Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 21.2 Process time 3.7 Inspection time 0.7 Move time 3.3 Queue time 5.4 The manufacturing cycle efficiency (MCE) was closest to:

User Glagolig
by
3.9k points

1 Answer

3 votes

Answer:

the manufacturing cycle efficiency (MCE) is 0.28

Step-by-step explanation:

The computation of the manufacturing cycle efficiency (MCE) is shown below:

Manufacturing cycle efficiency is

= Value-added time (Process time) ÷ Throughput time

= 3.7 ÷ (3.7 + 0.7 + 3.3 + 5.4)

= 0.28

Hence, the manufacturing cycle efficiency (MCE) is 0.28

We simply applied the above formula so that the correct value could come