Answer:
greater than 70% but less than or equal to 90%
Step-by-step explanation:
The computation of the capacity utilization rate for process X is shown below:
As we know that
Capacity Utilization = (Actual Output ÷ Design Capacity) × 100
= (786 ÷ 1026) × 100
= 76.61%
So, it is greater than 70% but less than or equal to 90%