The following is a list of six control plans.

Control Plans
a. Review shipped not billed sales orders
b. Turnaround documents
c. Deposit slip file
d. Procedures for rejected inputs
e. Computer agreement of batch totals
f. Document design

These are followed by a list of five statements describing either the achievement of a control goal (i.e., a system success) or a system deficiency (i.e., a system failure).

Control Goals or System Deficiencies
1. The shipping clerk could not read the quantity picked that had been written on the picking ticket by the warehouse clerks.
2. In a periodic/batch environment, helps to ensure the information system control goal of input completeness of the shipping notices.
3. Helps to ensure that all shipments are billed in a timely manner.
4. Meets the operations system control goal of efficiency of resource use by reducing the number of data elements to be entered from source documents.
5. Provides an "audit trail" of deposits.


Match the five control goals or system deficiencies with a control plan that would best achieve the desired goal or prevent the system deficiency. A letter may be used only once, with one letter left over.

User Sdlins
by
4.1k points

1 Answer

1 vote

Answer:

1. f. Document Design.

2. e. Computer agreement of batch totals.

3. a. Review shipped not billed sales order.

4. b. Turnaround documents.

5. d. Procedures of rejected input.

Step-by-step explanation:

The business in todays world has to meet customer demands in order to be successful. It should deliver goods timely and the processing lines should be efficient. The employees should work efficiently and should be able to complete their assigned tasks within time. There should be strict internal controls to avoid errors and frauds. When shipping clerk is unable to read quantity there should be defined document design which clearly shows the quantity in bold on the ticket.