The graph represents the force applied on an 3.00kg crate while it moved 5.0m. A. How much total work is done on the crate? B. If the ball was moving at 6.00m/s when the force was first applied, what is its final velocity?​

The graph represents the force applied on an 3.00kg crate while it moved 5.0m. A. How-example-1
User Defvol
by
2.7k points

1 Answer

25 votes
25 votes

a. We can calculate the amount of work by calculating the area under the graph.

first area (rectangular): 2.5 x 6 = 15

second area(trapezoid): 1/2 x (6+10) x 2.5 =20

total work done: 35 J

b. the force was first applied = 6 N

F = m.a

a = 6 : 3 = 2 m/s²

vf²=vi²+2as

vf²=6²+2.2.5

vf²=56

vf=7.5 m/s