If 5 men complete a task in 3 days, how long

would it take 2 men, working at the same rate,
to complete the same task?
Answer​

User Blue Robin
by
5.4k points

1 Answer

0 votes

Answer:

7.5 days

Explanation:

Total mandays needed

5 men complete a task in 3 days

5 * 3 = 15 mandays

2 men, working at the same rate,

15 / 2 = 7.5 days