Answer:
Technology C
Step-by-step explanation:
Total Cost = Fixed Cost + Variable cost * (Number of Units)
Total Cost for Technology A = $80000 + $2.20*(100,000 units)
Total Cost for Technology A = $300,000
Total Cost for Technology B = $120,000 + $1.85*(100,000 units)
Total Cost for Technology B = $305,000
Total Cost for Technology C = $130,000 + $1.65*(100,000 units)
Total Cost for Technology C = $195,000
Conclusion: The minimum total cost for 100,000 Unit is for process technology C, Hence this technology would be recommended