Answer:
Option 2, In seismic areas, the most crucial requirement for precast concrete is to tie elements together laterally
Step-by-step explanation:
In seismic areas, the in-plane lateral forces are very larger and hence in order to restrict the lateral movement governed by the lateral force, lateral ties are essential .
Specific design detailing such as interior and perimeter ties in the floors causes diaphragm behavior and hence distribute the load evenly without any movement.
Hence, option 2 is correct