75.0k views
2 votes
The following labor standards have been established for a particular product: Standard labor hours per unit of output 4.3 hours Standard labor rate $ 17.80 per hour The following data pertain to operations concerning the product for the last month: Actual hours worked 6,300 hours Actual total labor cost $ 112,770 Actual output 1,400 units Required: a. What is the labor rate variance for the month

1 Answer

5 votes

Answer:

See below

Step-by-step explanation:

With regards to the above, labor rate variance is computed as;

Direct labor rate variance = (Standard rate - Actual rate) × Actual quantity

Given that;

Standard labor rate per hour = $17.8

Actual hours worked = 6,300

Actual total labor cost = $112,770

Actual rate = $112,770/6,300 = $17.9

Therefore,

Direct labor rate variance = ($17.8 - $17.9) × 6,300

= $630 unfavourable

User JGrinon
by
6.1k points