The Maryville Construction Company occupies 105,800 square feet for construction of mobile homes. There are two manufacturing departments, finishing and assembly, and four service departments labeled S1, S2, S3, and S4. Information relevant to Maryville is as follows: Allocation Department Area used S1 S2 S3 S4 Finishing Assembly S1 18,600 --- 0.20 0.10 --- 0.10 0.60 S2 5,050 --- --- 0.40 0.40 --- 0.20 S3 10,100 0.20 0.20 --- 0.30 0.20 0.10 S4 5,050 0.20 0.10 0.20 --- 0.30 0.20 Finishing 30,150 --- --- --- --- --- --- Assembly 36,850 --- --- --- --- --- --- Rent paid for the area used is $736,000. How much rent is allocable to the assembly department using the direct method of allocation

1 Answer

2 votes

Answer:

$404,800

Step-by-step explanation:

Calculation to determine How much rent is allocable to the assembly department using the direct method of allocation

Using this formula

Rent =Area used by Assembly department / Total Area used by Manufacturing Departments x Total Rent paid

Let plug in the formula

Rent =36,850/ (36,850+30,150) x $736,000

Rent=36,850/67,000*$738,000

Rent=0.55*$736,000

Rent= $404,800