A concrete pilar has the shape of a svinder It has a diameter of 6 meters and a height of 5 meters. If concrete costs $108 per cubic meter, how much did the

concrete cost for the pillar?
If necessary, refer to the list of cometry formulas
For your calculations, do not round any intermediate stops, and use the it button on the ALEKS calculator Round your answer to the nearest cent.

User Otporan
by
3.1k points

1 Answer

1 vote

Answer:

The cost of concrete for the pillar would be $ 15,260.40.

Explanation:

Given that a concrete pillar has the shape of a cylinder and it has a diameter of 6 meters and a height of 5 meters, if concrete costs $ 108 per cubic meter, to determine how much did the concrete cost for the pillar the following calculation must be done, knowing that the volume of a cylinder is calculated with the following formula = πxr²xh:

3.14 x (6/2) ² x 5 = X

3.14 x 3² x 5 = X

3.14 x 9 x 5 = X

3.14 x 45 = X

141.3 = X

141.3 x 108 = X

15,260.4 = X

Therefore, the cost of concrete for the pillar would be $ 15,260.40.