Solution :
Given :
The production output per day = 75 units
Production time per day = 24 hours
Therefore, the cycle time is
=
![$\frac{\text{production time per day}}{\text{outpu}t \text{ per day} }$](https://img.qammunity.org/2022/formulas/business/college/e9g7mr3ef4mvvaehtj45lsv6ncncflzzwd.png)
![$=(24 * 60)/(75)$](https://img.qammunity.org/2022/formulas/business/college/n8meiu6z4f51p3ork2c1l2cleofbd2u3ug.png)
= 19.2 mins
≈ 20 minutes
The desired cycle time = 15 minutes per unit
Given the task times of A to E from the table.
Sum of the task times (A to E) = 4 + 3 + 5 + 5 + 3
= 20 minutes
Number of workstations needed = (sun of total task times) / (cycle time)
![$=(20)/(15)$](https://img.qammunity.org/2022/formulas/business/college/4avgl57263198551aadoi53mvxso5jkstq.png)
= 1.33
≈ 2 work stations