Answer:
$41
Step-by-step explanation:
Conversion costs = Direct labor + Manufacturing overhead
Manufacturing overhead = Variable manufacturing overhead + Fixed manufacturing overhead
Manufacturing overhead = $15 + $6 = $21
Conversion costs = $20 + $21 = $41
Therefore, estimated conversion costs per unit
= $41