The controller of Hendershot Corporation estimates the amount of materials handling overhead cost that should be allocated to the company's two products using the data that are given below:Wall Mirrors Specialty WindowsTotal expected units produced 12,900 1,500Total expected material moves 1,290 1,400Expected direct labor-hours per unit 9 12The total materials handling cost for the year is expected to be $16,754.50.If the materials handling cost is allocated on the basis of direct labor-hours, the total materials handling cost allocated to the wall mirrors is closest to: (Round your intermediate calculations to 4 decimal places.)Multiple Choice

1 Answer

2 votes

Answer:

$14,506

Step-by-step explanation:

Calculation to determine what the total materials handling cost allocated to the wall mirrors is closest to:

First step is to calculate Material handling cost per labor hour

Material handling cost per labor hour = $16,754.50 / [(12,900 * 9) + (1,500 * 12)]

Material handling cost per labor hour =$16,754.50/(116,100+18,000)

Material handling cost per labor hour = $16,754.50/134,100

Material handling cost per labor hour =0.124940

Now let calculate the Materials handling cost allocated to wall mirrors

Materials handling cost allocated to wall mirrors = 12,900 *9*0.124940

Materials handling cost allocated to wall mirrors = $14,506

Therefore the total materials handling cost allocated to the wall mirrors is closest to:$14,506