Answer:
Actual Quantity= 151.57
Actual Rate= $3.17
Step-by-step explanation:
Giving the following information:
Standard Hours 2.50
Standard Rate $35.00
Standard Cost $87.50
Number of tune-ups= 60
Labor rate variance $ 50 F
Labor spending variance $ 55 U
First, we need to calculate the actual number of hours. We need to use the direct labor efficiency variance:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
-55 = (60*2.5 - Actual Quantity)*35
-55 = 5,250 - 35Actual Quantity
35Actual Quantity = 5,305
Actual Quantity= 151.57
Now, the actual hourly rate. We need to use the direct labor rate variance formula:
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
50 = (3.5 - Actual Rate)*151.57
50= 530.5 - 151.57Actual Rate
151.57Actual Rate= 480.5
Actual Rate= $3.17