The scope of latisha's project changed by +25%. The approved change request called for 1000 units to be produced. What was the amount of the initial project scope?.

User Rkz
by
4.6k points

2 Answers

4 votes

Answer: The amount for the initial project scope was 800 units.

Explanation: Since 200 units is 25% of 800 units, and 800 units plus 200 units equals 1000 units, your answer is therefore 800 units.

The scope of latisha's project changed by +25%. The approved change request called-example-1
User Jonathan Peterson
by
5.5k points
7 votes
C. 800 units welcome