Exit Ticket An art project takes Misty 4 hours to complete. She works for 3 hour each day. How many days does it take Misty to complete the art project? 4

User Cryp
by
3.3k points

1 Answer

6 votes

She works for 3 hours each day.

The art project takes Misty 4 hours to complete

Let's call x to the number of days she needs to complete the project

The next equation model the situation

3x = 4

Solving for x:

x = 4/3 days