477,594 views
3 votes
3 votes
Two teams working together can finish a job in 8 days. if the first team works alone for two days and the second team works alone for 5 days, 5/8 of the total work still remains. How many days will it take each team to finish the work alone?

User PSL
by
2.6k points

1 Answer

21 votes
21 votes

x is the days that the first team finishes the work alone (x>8)

y --------------------------second-----------------------------------------(y>8)

In a day:

  • The first team finishes 1/x (the work)
  • The second team finishes 1/y (the work)
  • Two teams working together finish 1/8 (the work)


(1)/(x)+ (1)/(y) =(1)/(8) (1)

If the first team works alone for two days and the second team works alone for 5 days, 5/8 of the total work still remains:


(2)/(x)+(5)/(y)=(3)/(8) (2)

(1),(2) ⇒
\left \{ {{(1)/(x)+ (1)/(y) =(1)/(8)} \atop {(2)/(x)+(5)/(y)=(3)/(8)}} \right. <=>\left \{ {{x=16} \atop {y=24}} \right.

It'll take the first team 16 days and the second team 24 days to finish the work alone

ok done. Thank to me :>

User Ricardo Veguilla
by
2.7k points