length od the tunnel = 3200 ft
after 5 months they need to dig 1700 ft more.
First, calculate the ft dug
3200-1700 = 1500 ft
Apply the rate
ft / time
1500 / 5
For the total length:
3200/ t
Equal both rates:
1500/5 = 3200/t
t = 3200 / (1500/5)
t= 3200/ 300
t= 10.6 months